***This is the final Northeast Region weekly highway construction update for 2021, these will resume in Spring 2022***
November 17, 2021
Questions? Please contact, Kurt Peters, WisDOT Northeast Region Project Manager, at 920-362-1157 or kurt.peters@dot.wi.gov.
WIS 23 Expansion Weekly Updates
WIS 23 Expansion
FOND DU LAC COUNTY
WIS 23 Expansion
Location/limits: USH 151 to Seven Hills Road
Length: 5.59 miles
Cost: $35 million
Schedule: Contract Completion Date of November 15, 2022
FOND DU LAC COUNTY
WIS 23 Expansion
Location/limits: USH 151 to Seven Hills Road
Length: 5.59 miles
Cost: $35 million
Schedule: Contract Completion Date of November 15, 2022
Description of work: This work is part of the WIS 23 4-lane, on-alignment expansion project in Sheboygan and Fond du Lac counties. Construction in the Fond du Lac urban section of the overall project includes the construction of WIS 23 additional lanes. Work also includes construction of a roundabout at WIS 23 and Wisconsin American Drive, a jug handle interchange with roundabouts at WIS 23 and County K, and a WIS 23 structure over County K. At WIS 23 and County UU, a diamond interchange with roundabouts and a bridge over WIS 23 will be constructed. Other work includes grading, drainage culverts and inlets, aggregate base, concrete pavement, and incidentals.
WINTER 2021/22:
The contractor will continue working on the new County UU bridge. The contractor will also continue working on miscellaneous grading and drainage items as weather permits.
Traffic impacts:
WIS 23 will remain open with a single lane of travel in each direction from Highway 151 to Seven Hills Road.
Hilltop Drive access to WIS 23 will be maintained on a temporary connection with Whispering Springs Drive.
Winter closures:
- County UU (south of WIS 23) – Closed
- County UU (north of WIS 23) – Closed
- County K (north of WIS 23) – Closed at Highway 23
- County K (south of WIS 23) – Access to and from Highway 23 westbound is closed.
Access restrictions will continue at the below locations. Posted “no left turns”.
- Southbound Whispering Springs to eastbound WIS 23
- Eastbound WIS 23 to northbound Whispering Springs
Project website: https://projects.511wi.gov/wis23resurface/
Statewide traffic impacts and construction projects
- https://511wi.gov/ or call 511
Please use alternate routes to access these locations.
For more information on the project please visit the following website:
https://projects.511wi.gov/wis23resurface/
Looking for real-time updates of the expansion project? Click here.
Contact Us
Please note, there will be restricted access to campus during the summer.
Business Office –
Greg Brunette – Business Office
920-322-8078 Tuesday and Wednesday from 7:30 a.m. – 3:30 p.m.
Please note, due to construction, please mail all payments to:
St. Mary’s Springs Academy
Attn: Business Office
255 Cty. Road K
Fond du Lac, WI 54937
Scrip –
Chris Gilles ’83 – Scrip Coordinator
As of Monday, June 7th, the Scrip Office will be temporarily located inside Holy Family’s Parish Office (271 Fourth Street Way).
Hours of operation will be: Mondays 8:00 a.m. to Noon and Thursdays Noon to 4:00 p.m.
Want to know more about Scrip? Click here!
Athletics – Please contact your child(s) coach with any questions you may have.
Greg Hoffmann – Athletic Director
System Communications
Summer Parking on Campus – beginning Monday, June 14, 2021